| Ankeny
High School / YMCA - Construction Progress - (Updated
8-26-03) |
| [The Ankeny High School/YMCA
addition is shared in cost with the YMCA and funds from the One Cent
Local Option Sales Tax .] |
|
|
August 25, 2003 - This view is of the southeast
corner of Ankeny High School and the main entrance to our Ankeny
Family YMCA. This is where the main part of the addition will be
located.
|
August 25, 2003 - This picture shows work
just beginning on this project. The addition will provide a bonafide
weather protected main entry to our High School from the south,
additional space for physical education and student activities,
added locker room space, an added classroom, and much needed
additional space for the YMCA. Our School District and YMCA are
sharing the
$4.3 million cost.
|
|
|
August 25, 2003 - The addition will add nearly
40,000 sq. ft. Much of the existing adjacent area will also be remodeled,
as part of this project.
|
August 25, 2003 - These are forms for the foundation for
the new addition. The goal is to have the roof in place before
winter to keep the progress schedule moving forward and on time.
|