Construction Update – Oct. 2021

Exciting progress is being made daily on our ongoing construction projects.

High School Additions: The construction at the high school editions is 95% complete, with the majority of remaining tasks focusing on organizing and outfitting classroom spaces to individual teacher preferences. The weight room is also essentially complete, with only a few final touches remaining.

At Parkview Middle School, we estimate that 80% of renovation to classrooms is complete. The band/choir room will be accessible on 10/18 and the last set of restrooms will be complete on 11/1. The front office area is complete and is being housed with temporary furniture. New furniture for these areas is expected to arrive in mid-November, in addition to new media center shelving. The final project is the locker room, which is expected to be complete by 11/11.